On-site dehumidifier for water infiltration in a building under renovation
What was the customer’s problem?
Water infiltration in the roof slowed down construction of a new 1365M² winegrowing building.
To achieve this, we installed dehumidifiers coupled with a heating system to enable the building to be cleaned up so that the various works could be resumed.
Equipment set-up and field action
We have installed a 185 kW hot air generator positioned outside the building and operating on air recirculation, and 8 1080 m³/h dehumidifiers with a dehumidification capacity of 120L at 30°C and 80% RH. Each dehumidifier is fitted with a condensing hose for total autonomy.

Fast, efficient response
It took just one day to install all the equipment. A team of 2 technicians was on hand. Ask us for advice on dehumidifier rental.